Friday, 23 March 2018

Operating Days

As we move towards warmer weather it's time to plan your visit to take a ride on the railway.
Here are the operating days at both sites.

Firstly are the dates at Llynclys
 Then we have the dates at Oswestry

First trains are 11am and at half-hourly intervals until 3:30 or 4.  Full details are on the CHR website.

The special events kick off with an Easter Egg hunt on Easter Sunday.  Each child taking part with an adult in the hunt will receive a free Easter egg

Around the railway work is ongoing but the cold and snow has meant a certain slowing down of activity, however we are expecting work to start shortly on the excavation works to lower the track bed.

Tuesday, 13 March 2018

Choices, Choices

Pictures will be coming later but there was much activity during the 'Big' working weekend, the plan was to get ready for the arrival of heavy plant.   During the weekend we were faced with the ongoing debate about gauge supremacy so to end it all an experimental section was laid to determine the feasibility.  So far we have 5", 7 1/4", 10 1/4", 15", 2ft, 2ft 6", 3' and 4 feet 8 1/2".

The head of the PWay team, on looking at the results, was a bit sceptical and when someone mentioned that points might be a bit of a challenge was last seen taking big steps towards the Highwayman for serious refreshment...

Edit:  Here's the idea...



Any more suggestions for gauges to incorporate??

PS Thanks to Tony J for the picture and the idea.  Or did somebody put something stronger in the tea this weekend..

More soon.

Thursday, 1 March 2018

A Brief Interlude

Although the weather is cold outside plenty is still going on around the railway.  I thought that you may be a bit overfed with coach stories so here are some other items going on along the line.

The station at Llynclys has had a spruce up to get ready for the operating season.  The team have been putting to good use the contents of the paint store, bringing colour to various items around the site. The speed restriction signs have had some attention and should now stand out against the snow sweeping across the country,

The steps to the platform have had the railings painted and white lines reapplied on the steps and platform edges.

Even the doors are having some attention and Chief Inspector Lenny the cat approves of the work done

Anyone who would like to get involved would be warmly welcomed and don't worry there is plenty of tea also there.  Thanks to the CHR Facebook page for the pictures


For anybody who reads the local papers the CHR is again taking part in Shropshire Star's Cash for Your Community 2018 campaign.  All you need to do is collect the tokens as they appear in the paper and drop them off at Oswestry station in an envelope marked for Cambrian Heritage Railways, or pop in and see what is going on.

More details are on the Facebook page
https://www.facebook.com/cambrianheritagerailways/

Whilst we wait for better weather it is maybe an idea to take a short trip along memory lane with Tony, one of out active volunteers.  Here is his cine film of the line in January 1965.

https://www.youtube.com/watch?v=hPRyOzqXk7Y

That made me chuckle as I was born one month later and I am not exactly a teenager.  Along the way you can see how much has changed with buildings and greenery now lining most of the route.  We have our work cut out to get back to those days but we are making progress.

Until next time.

Friday, 23 February 2018

The People's Coach

The working weekend came and went and under clear weather there was a good turnout, Saturday tackled the lineside growth down at Llynclys.  The next big working weekend should be back on the extension at propped gasworks bridge.  See the end paragraph.

More pictures arrived from Glynn of work last Thursday.  Glynn was getting his own back on Andy, one of the other sources of blog photos, by taking pictures of him as he worked on the bodywork. 

First here is Andy seeing that the peep holes are in line to check on who walks past the kettle without offering to make a brew.  Andy had been drilling out rusty bolts to get at the window frame seals.  There are a few still to go.  In the background Alan on the bench and John on the floor carry on with prepping the axlebox covers.
Meanwhile John A continues work on the cleaning up of the bogies and springs, it's a mucky job but we will get there.
We do occasionally allow people out for air, here are Davey, Dave and Noel basking in the Oswestry sunshine planning the next assault.
On Sunday the team were back in action again on the coach and with the almost tropical temperatures it was decided to open the roller doors and let some air through.  In the dappled sunlight Reg is preparing and filling the coach end ready for priming.

Glyn (single N) was attacking the doors to remove loose paint and rust.  Almost all of the main body is now done so the doors are the next on the list.

Chairman Rob was back in more usual clothes after recent fame and a major spread in the local paper.  It's not every day we get £120k so we do need to thank our supporters, past, present and future. With Glyn on the doors Rob was relieving the frames so that the doors shut with that satisfying clunk.  Modern trains with sliding doors just don't have the same effect on me as a good click, click clunk from a wooden door.
Phil having got over the Cambrian Christmas Lottery (did you win?) was back in the guards compartment sanding and scraping after having removed window frames.


Thanks to all who turned up for work inside and out and hope you enjoyed the sunshine that was laid on.  No promises for next time though.

Moving on to future work we have a big weekend coming up on the 10/11th of March.  It will be all hands to the pump with Kevin and helpers as we get ready for the start of heavy earth moving.  The whole work site needs to be got ready so this will mean lifting 4 lengths of rail at the current railhead.  On the other side of the bridge the area needs to be cleared of stored sleepers and other track items.  This will allow the heavy plant access in the following weeks.  The most important item, the mobile brew station, has been placed on red alert.

Until next time.

Friday, 16 February 2018

Sitting Down on the Job

The Thursday gang again concentrated on the coach this week and thanks to Andy G here are pictures of the work in progress.
First is a general view of how the exterior is looking at the moment.  Plenty to be getting on with as we would not to let the crew get cold standing around.  This time jobs seem to have been concentrated on those which can be done from sitting positions.


Next you can see along the solebar and where the 'tin worm' has been cut out.  Rot along these bottom edges is not uncommon on Mk 1's of a certain age as water and muck tend to collect along the bottom edge and corners of the body 
Following cleaning a coat of primer is put on to the bare metal, here the invisible man, hogging the deckchair, has just finished the V hanger whilst the next strap is being worked on from a less comfortable pallet seat.


Attention was also turned to the mechanical condition and axlebox covers removed for an inspection of the journal, again notice the effective us of seating, which is of great use when the inevitable mug of tea appears.

Higher perches are used for work further up the coach body and we have to be inventive.  Being sat comfortably is better than working with arms above shoulder height.


The journals have seen the light of day and there will be some attention needed before these enter service.

With everybody sitting down today we had run out of chairs so the team removing the axlebox covers had to stand or kneel.  You can also see the bottom edge of the body marked up for removal of the corroded section.  That will be for another day.

This weekend the working party will be outside working on vegetation clearance, weather permitting.  The kettle has been placed on high alert and is ready for action.

Until next time.

Friday, 9 February 2018

Coach(ing) Sessions

We now have two working days mid week on Tuesdays and Thursdays, Glynn and team on Tuesdays and Dave and team on Thursdays.  Progress has accelerated so many thanks to those who come mid week.  Maybe we need to call them the TT gang as they are certainly cracking on at high speed.

Activities this week have mainly centred on the coach and thanks to Andy G for the pictures.

Work on removing the comfy bits is almost complete, not many more cushions to go.  Now you can see the open nature of the coach construction, the compartments are mostly separated by the seat backs.


Here are the innards, now open for all to see, whilst generally in good condition internally attention will be given to restoring the woodwork and making it a pleasure for our guests on their trip to Weston.

It is an almost unwritten rule that you clear out any space and somebody will find something to put in there, here is proof as the seats are now placed in safe storage whilst the dirty work of stripping, sanding and coating the internal woodwork is being done.


Here Big John and Alan close the doors on the seats 'See you very soon in the restored interior'
Already cracking on with restoration Big John sands down picture/mirror frames of which there are quite a few, six to each compartment, That's a job that will go on for a while.

Meanwhile Colin and John are working in the guard's compartment. Now you can see the benefits of being under cover, imagine working like this with the doors open outside in February. We are not sure if John was about to jump or just being camera shy.
 Actually no, John was busy working and has been preparing the inside to assess it's condition.

Not only the inside was worked on, underneath was given some attention as well.  Here is Noel de-rusting and scraping the bogies. 
There is lots of work still to do but the tea and banter are flowing well.  The kettle is now at arms length and rarely gets cold. 

Elsewhere work continues around the work sites preparing for the next tracklaying push and tidying up to get ready for the operating season.

The two days planned for this weekend have been pushed back by one week due to the weather, same plan to get lineside clearance done before we have to stop for nesting season.  Work needs doing alongside the running line at various places so this is where the effort will be concentrated.

Until next time.

Thursday, 8 February 2018

Beams in Place

The delivery last weekend has already been put to good use.  After unloading the beams were very soon put in place across the gaping chasm of the cattle creep. With that we now have a sound continuous base from just south of the propped bridge until Weston.  Here are the beams in all their glory spanning the gap.

Thanks to the CHR Facebook page for the picture
Included with the beams were additional stiffeners and location beams that hold everything together.  It will be a few months before we can run trains again over the bridge, there is plenty of track to (re)lay and ballast to screen before then.

Elsewhere work continued on other parts of the project, with Tuesday now being added to the working calendar.  Glynn and helpers have been carrying on with more work on the coach.

Until next time