Tuesday, 9 October 2018

North of the Bridge

As the sign says we are now ready to go, looking towards Oswestry we will take a very short trip along the regarded line, starting at the sleeper stack.

Just beyond the sleeper stack is the concrete cap of the sewer crossing, now safely embedded under a concrete protection shield. The sides of the line will soon return to nature softening the effect, eventually even the gabions will merge in to the lineside.
At the end of the currently available section is the Gasworks Bridge, still having some work done on the steelwork.  This will be completed very soon and the fencing removed to allow us to progress to Weston. 

 A helmet has been left on the ladder, so someone will return!
Could it be the same person who left their gloves??  Maybe someone was in a real hurry to leave site that day.  Evidence of the sand blasting is all around with the steps taking on a new colour, or is this the new anti-slip coating?
Guy N again with the pictures, many thanks.

Now we have trackbed, ballast and sleepers.  Next steps are to assemble this in to a working railway.  Do you fancy lending a hand?

Until next time.

And Then They Were (Almost) Gone

The planned works under the bridge are almost finished and part of the trackbed is already waiting for ballast and track.

Firstly here is the run down from the railhead to the bridge.  In the foreground is the sleeper stack at the current end of the running line.

The cover over the sewer is in place. 
The cutting sides have been re-profiled and gabions installed to retain the earth.

The bridge is still having a few cosmetic touches to finish the painting.

More pictures later in the week of the other side of the bridge and the route to Weston.  Thanks to Guy N for the pictures.

Until next time.

Friday, 5 October 2018

Screened This Week

The week of screening has come to an end and the progress has been remarkable.  Firstly the machine has run as intended, which is payback for the volunteers who invested time and money to purchase the machine and carry out the necessary overhaul. There have been quite a few people involved this week and a fair few visitors.  Colin took these pictures at the close of play on Thursday.

The first picture shows three freshly mined piles of ballast with the resulting spoil next to them. 
The next picture is looking the other way, back towards Oswestry, with the piles heading off in to the distance.  As you can see the distance from base increases so transport becomes necessary to reach the work site.
Looking south you can see what is left to screen on this section. Just beyond Betsy the excavator is the cattle creep.  There is another day of work to screen the ballast on this section.
Lastly is a picture from Glyn W showing the piles in the setting sun.  The total for the week was 17 ballast piles.  That means that overall we have 23 mounds of ballast ready to be used. 

Thanks to everyone who helped during the week and special mention to Glyn for driving the excavator.

Until next time

Thursday, 4 October 2018

Piling it On

A quick feedback from the screener.  This week the unit has run very well and with another day of work we should reach the cattle creep.  That will be over twenty piles completed.  Pictures to follow and possibly some video.  Well done to all involved.

Wednesday, 3 October 2018

The Moles Are Back

This week will see the contractors move off site and hopefully hand back the section ready for track laying.  In advance of this we have been giving the screener a work-out, so far so good.  Glyn W has been active with the JCB and bucket keeping the machine fed.  Here is Glyn in mid scoop with the mixture ready to be loaded to the screener. 



As you can see the screener is moving along the trackbed and the piles behind it are growing, it's those elephant moles back again!
 Here is an action shot of the output end with the segregated piles building up.
 Meanwhile the contractors continue with the tidying up operations ready to leave the site
Thanks to Andy G for the pictures.  There is considerable excitement and anticipation now as we wind up to restart work on the trackbed.  Muscles are already being flexed with preparatory work so why not come along to see or better still join in.

For future events we are gearing up for the winter season with our popular Santa Specials in December and a couple of open days before.  As well as the usual volunteer sessions on Thursdays and weekends there is a Big Working Weekend on the 20th/21st October at which it is hoped work will restart on the extension.

The CHR AGM will take place on the 10th November in the afternoon, all members invited.

Until next time.

Saturday, 29 September 2018

Finishing Off

Lots of jobs going on around the bridge, the trackbed is being rolled and prepared. There was also an additional visitor as a bird of prey had lunch alongside the track.

Firstly the drains are now all covered and the track base is being rolled, the tidy up of the site has also begun with some items being positioned ready for removal
The level boards are back to be able to set the final track and ballast levels
Work goes on with grading and levelling the trackbed with the dumper bringing in additional fill as required.
This small roller has being in action consolidating the ground under the trackbed
Here you can see the rolled bed ready for ballasting

The trackbed has been used by many creatures.  Here a sparrow hawk has lunch following a hunt along the railway.  He barely stopped as Guy took the picture.

Under the bridge work is continuing with the sandblasting and painting of the steel work
The whole of the steelwork is being painted to ensure another trouble free pair of decades or so
Even the detail wok of the jacks are being prepared and painted.
Here you can see some of the beams already finished
The sandblasting equipment is standing by ready for another bout.


Here we are looking along the compacted trackbed, ready for final rolling and ballast.



Here is a rolled section, not long before the team start to lay track.


Help is on hand for moving earth and ballast
A view back along the track as various jobs are finished off.
Thanks to Guy N for the pictures.

Until next time

Tuesday, 25 September 2018

Three Steps

There are still a further few items being worked on relating to the Gasworks bridge.  Guy N took some pictures of some of the recently cast features around the bridge, first an overall view of progress.
In the second picture notice the three cast-in steps to the left to give access under the bridge, very neat.
Here is an overall view of the bridge works with the access tower in place for inspection and fettling of the underside.
Looking south the works are progressing, we are on the home straight now
Thanks to Guy for the pictures.

Until next time.