Friday, 31 May 2019

Thursday Gang

Thursday continues with it's regular pattern with work going on at both Oswestry and Weston.  The team at Oswestry got stuck in to preparing panel eleven on the centre road.  The rail was brought up from the store and moved in to the freshly laid out sleepers.  Andy G took the following pictures as with one rail in Noel, John, Keith, Steve, Julian, and Norman work on moving the second rail to where it will be needed.

The team takes a bit of a breather with the second rail now lying in the 'four foot'.
 Inside Keith and Alan continue on the suburban coach.

Out of sight of the camera the drainage catch pits in the station area received attention, the wagon refurbishment continued and a squad of four went to Weston to dismantle some track.

Thanks to all who took part and to Andy for the photos.

Until next time

Wednesday, 29 May 2019

Tuesday Gang

Team Tuesday carried on around the site working on finishing panel ten and getting material ready for further work. Glynn was in action with the Hiab to move rails around and create storage space for track materials.

In the first picture from Andy, John, Tom, and Noel take a breather having carried on with completing the keying up.

Once the work is completed Noel and Norman take a look at their handiwork.  Now doesn't that just look so good?
Many thanks to all who turned up under sunny Oswestry skies and to Andy G for the pictures.

Until next time.

Tuesday, 28 May 2019

There She Blows

Over the bank holiday weekend we took another small step on the way to Weston.  The limit of operation of the running line was extended down to Gasworks Bridge.  This is a fitting reward for all who have helped with this project and it was good to see smiles on the faces of the volunteers and customers on these runs.  Guy N was on hand and took the following pictures of the event.

We start with a look south along the line towards the bridge.  The Stop board has been positioned and the track has been jacked and packed where necessary.  The track has been inspected and tested and we are ready to go.  The only thing missing is a passenger train.

In the distance the whistle blows and the sound of the steam loco can be heard making it's way along the line.
The loco and train eases up and creeps along to the end of the line.
 There we have it, a steam loco on the new track, time to set off back to the station.
What a wonderful tribute to the hard work of so many people in all roles who made this happen, take a deep bow.  Then take a deep breath as we push again on the way to Weston.

Until next time.



Squeezing One In

One of the leftover jobs from the work under Gasworks Bridge was to install an additional concrete sleeper to the south to support the rails.  The team tackled this job and Guy was on hand to take a picture once completed.   This meant a bit of a shuffle with the sleepers and an inverse game of Mikado (the one where you have to remove sticks without moving the rest) as the sleeper has to be threaded under the rail without causing disruption.  Just to add to the fun access from the sides is limited by the steps and supporting wall.

It was a bit of a wiggle but in the end, as you can see in the picture, the sleeper is in and the rail clips are now evenly spaced, ready for trains.
There is still plenty to do with preparing the track for passenger services.  The line needs to be finally packed and tamped but the way ahead is now clear.
Thanks to Guy for the pictures.

Until next time

Monday, 27 May 2019

A Little Bit of Weston

With a fair wind we should soon be starting work at Weston on the upgrading of the site, adding facilities which will allow us to welcome guests.  Before the work starts we have a couple of pictures which we can then use for a comparison on completion of the modifications.  Thanks to Guy and Noel for the pictures and information.

We start with the view of the line arriving from Oswestry.  In the background can be seen the row of poplar tress that have been in the distance of photos taken from the recently replaced cattle creep.  The long straight run down to Westin ends just before the station in a gentle curve.  The recently moved tank wagon rests at the entrance to the station.  Hopefully it won't be too long before we see loco hauled trains arriving here.

Looking the other way we see the site at Weston with the raised area to the right which will become the platform.  There are already materials on site for the trackwork but the platform wall will need stabilising and rebuilding.  The wall shows the many changes that have occurred over the years at Weston.  A simple loading dock was extended and then raised/extended again resulting in a variety of heights and stability.  The brickwork on some sections is poor to say the least, on other sections it has already collapsed.  The only solution acceptable to be able to use for passengers is to rebuild starting from new foundations.  
The new platform will also house the new toilet block which will be a welcome relief for all and possibly of vital importance given the brewery next door. The track layout will consist of a run round loop on the left side of the picture and a bay platform to the right of the running line. 

The goods shed will become a useful space for conservation and restoration work and the small office will be used to show the history of the site and house the station office.
 
There is a great deal of work still to be done and although we have received a grant to cover a lot of the cost we still need to raise around £30k to complete the works.  All donations are welcome.  Timing will depend on how quickly we can raise the money but we hope by next year to be well on the way to having Weston station ready for trains.

Thanks to Guy for the pictures.

Until next time.

Thursday, 23 May 2019

Thursday Gang

Twelve volunteers turned up on Thursday to continue with work around the station.  There were three main activities.  Work on the Suburban coach continued inside the shed.  The Dogfish wagon was given further attention and a further panel of track was assembled on the centre road.  Andy G took a couple of pictures.

The first shows the arduous job of supervision, it takes years of practice to become this proficient and there is a long list of potential applicants, all able to expertly drink tea.  The training is intensive and competitive interviews were conducted as to who was the most suitable to sit in a chair and drink tea.  It was a hard fought contest but Davey J just edged it.  Here he is in classic supervisory pose watching the rest laying track whilst offering suitable works of encouragement, which were given equally suitable words of reply.

At the sharp end it was time for another panel to be laid, after a burst of activity the team take a rest whilst Steve works on the fishplates.  Norman, John, Noel, Mick and Tom have a chat about the next panel.  We are going to need more sleepers before too long.
The centre road is making progress and it won't be long before we reach the curve, still some way to go though.  If you fancy joining in get in contact or come along and take a ride.

Many thanks to the twelve volunteers who came along to enjoy the sun and to Andy G for the pictures.

Don't forget the Model Railway Exhibition on the 2nd June, trains of all scales will be operating.

Until next time.

Tuesday, 21 May 2019

Tuesday the 9th

But Tuesday was the 21st you say, not the 9th. That is true but in Oswestry we were toasting the 9th.  The volunteers restarted work on the centre road and installed panel number nine.

The day started with a shunt with Andy R at the controls of Telemon our trusty shunter.  Once the way was clear more rail was brought up to allow us to assemble another panel.

We start with a picture from Guy showing the end of panel number eight. This is just about in line with the north end of the station building.


The first job was a rail hunt. Once a suitable pair had been found it was time to prepare the ironmen for the lift. Here Norman keeps an eye on photographer Andy G whilst Andy R, John and Colin ready the ironman with Mick casting an eye over the proceedings.

Once the rails were loaded between the trolley and the frame it was time to move off and journey up the line. The team make their way over the single slip towards their destination.


With the first rail in position, Mick and Norman tighten up the bolts on the fishplate in the foreground whilst Tom, Colin and Noel are putting the keys in the chairs to hold the rail in position.
The second rail was then installed with Noel, Mick and Colin starting on the keys.
Just the last few to put in place.

That's it. Panel number nine completed. John, Mick, Andy R, Colin and Noel look happy with progress before returning to base to celebrate with a mug of tea.
Another panel of progress as we head north to complete the run round.

Thanks to all who braved the sunshine and to Guy for the first picture and Andy G for the rest.

Until next time.