Monday, 3 December 2018

Extension Pictures

›
Thanks to Guy N here are the latest pictures of the extension under the bridge.  Firstly we look back towards Oswestry with a very significa...
Sunday, 2 December 2018

December Arrives

›
Here we are, coming to the end of what was a glorious year for the CHR project.  We now move in to the month of December having achieved man...
Thursday, 22 November 2018

Thursday Gang

›
Another active and productive day in Oswestry. On the extension we welcomed another four loads of ballast which arrived to the access poin...
Tuesday, 20 November 2018

Santa Specials

›
Don't forget the Santa Specials.  Please support if you can as these help to fund future developments along the line.  Come along and jo...
Monday, 19 November 2018

The Start of Ballasting

›
Following the laying of the membrane last week the first two loads of ballast were placed in position.  Guy N took some pictures showing the...
Sunday, 18 November 2018

Coach Arrival Pictures

›
Here are a few pictures from Andy G of the unloading of the TSO at Oswestry.  Tony W and the team have been busy transforming this coach bac...
Wednesday, 14 November 2018

Llynclys Carriage and Wagon Delivers

›
Tuesday saw a new arrival at Oswestry, the TSO coach (Tourist Second Open) E4965 made it's move from the restoration base al Llynclys t...
‹
›