An informal blog about the work going on with the Cambrian Heritage Railways' (CHR) extension to Weston. This volunteer project aims to connect the existing running line to Weston Wharf where a station will be built. Copyright for the pictures remains with the original photographer

Sunday, 16 February 2020

Catch 22

›
Well it probably isn't catch point number 22 but we still need to build this before we can connect the sidings to the running line. Th...
1 comment:
Wednesday, 12 February 2020

To The Point

›
The three day week at Weston continues. Volunteers are working on site Tuesday, Thursday and Saturday as we build the new station. Recent ...
Tuesday, 11 February 2020

Be Prepared

›
Although it might seem quiet there is plenty of work going on behind the scenes. The planning of the activities needs to be worked out in or...
Thursday, 6 February 2020

S(l)iding Along to Weston

›
Down at Weston work to transform the site in to a working station continues every Tuesday, Thursday and Saturday. Sometimes it might seem li...
Monday, 3 February 2020

Platform Souls

›
It's February and we have so far been blessed with dryer weather than the rain at thr end of last year.  The dryer weather has allowed u...
Friday, 24 January 2020

Weston Works

›
The effort at Weston continues. There is much to do clearing the trackbed ready for the main running line to be laid. Years of growth need...
Tuesday, 21 January 2020

January Work

›
Although there are not so many picture updates so far this month there is still plenty of action both on the ground and behind the scenes. ...
‹
›