Monday and Tuesday.
More sleepers have been moved in to position along the freshly laid ballast bed. Working north from the cattle creep an extra 100ft have now been positioned. Glynn, Andy and Steve also lined up the freshly laid sleepers, dug out, cleaned and laid three pairs of rails in the 'four foot' ready for the track gang to drop in to position. The nearest sleeper is now 230ft north of the cattle creep.
In another delivery, forty special sleepers needed for the transition at the slab under the bridge arrived and have been placed in store.
Special thanks to the team that turned out to help and to Glynn for the picture.