Monday 17 September 2018

Filling The Gap

Over the last week there has been a fair amount of comings and goings making photography a little difficult.  The trackbed has been used to deliver the concrete which now fills the gap between the sheet piling. Here is a view along the trackbed with levels established, awaiting the ballast.
Under the bridge the centre piece of the slab has now been poured, this sets the track level so best to double check that stock will pass as intended.
The formwork also includes covers for services and keys in to the soon to be ballasted section of the running line.
 These areas will be finished off shortly.
Whilst the concrete was setting these temporary props kept the sheet piling sides apart, now the piling is secured both sides by concrete so these will be removed
 Looking back under the bridge you can see the slab in place, another part of the job completed.
Thanks to Guy N for the pictures.

Until next time.