Tuesday 3 December 2019

Weston Station

The work at Weston continues with the two sidings heading towards completion.  It is important to finish these sidings before the platform is assembled as access with mechanical plant will be severely limited once the platform has been installed.

Similarly work on removing years of growth and dumped materials is ongoing as we tidy up the site area.

Andy G was on hand to take a quick snap of the latest progress.  Work on the footings for the precast platform sections is underway and delivery is expected early in the new year.

The picture shows the view from the point looking south towards the new station.


Thanks to Andy for the picture and to all who joined in.

Until next time.

No comments:

Post a Comment