Friday 30 October 2020

Rainy Thursday

The weather on Thursday was a little damp but the enthusiasm was still there. Most of the work was related to preparing for next week when there will be a working week to tackle some significant projects 

Andy G's camera captured a few goings on during the day.

Down at the river bridge the wire fencing was being installed. Just look at how clear the site is now following attention by Dave, Nick and Norman under the heavy rain. 


The distribution of ballast continued with Glynn on the mechanical side and Glyn on the manual method. Now isn't that looking good?
    
The Lowmac was loaded with excess materials from track laying ready for the ballast to be dropped and the next phase of the project.


There has been impressive progress over the last year inspite of the difficulties. Long may this continue.

Thanks to all who braved the weather and to Andy for the soggy pictures.

Until next time.