Work on the Shrewsbury Road bridge continues, whilst the excavation goes on there has also been an opportunity to inspect and maintain the steelwork of the bridge. The scaffolding gives access to those points that would otherwise be difficult to reach.
At the foot of the columns the steel reinforcement has been installed and bolted back through to the concrete.
The last view shows the completed installation and also gives an idea of the amount that the trackbed has been lowered.
Thanks again to Guy N for the pictures
Until next time.
No comments:
Post a Comment